In Progress: Courtney Ave. Sewer Improvements Project
Project Overview
In February, sewer improvement construction will begin along Courtney Ave. between River Rd. and McLoughlin Blvd. Work is expected to be completed in the spring of 2026.
Purpose
Oak Lodge Water Services is replacing aging sewer mains along Courtney Ave. in Oak Grove. As part of the project, lateral connections from the main line within the public right-of-way to individual property boundaries will also be replaced.
Clackamas County is planning road improvements on Courtney Ave. in the near future, which may affect access to our underground infrastructure. To avoid disruptions, we are completing this work ahead of the County’s project.
The result: Replacing and rehabilitating aging infrastructure minimizes recurring maintenance issues and reduces long-term repair costs.
| Project Timeline | Total Cost |
|---|---|
| February 2026 - spring 2026 | $1,500,000 |
| Project Contact | Phone | |
|---|---|---|
| Ben Green | (971) 415-4953 | ben.green@olws.org |

Potential Project Impacts
Work hours: Monday-Thursday, approximately 7 A.M. - 5 P.M.
Sections of Courtney Ave will be closed while pipe replacement work is underway. Detour signage will be on-site directing traffic around the work area (crews will work with residents to maintain local access). If you are driving, biking, or walking in the area, please be alert and watch for construction crews, construction signs, and flaggers.
During construction, heavy equipment and materials will be in the work area, which will be marked with cones and/or caution tape. There may also be some noise and dust during construction hours.
On-site crews will communicate directly with homeowners about any direct impacts.
If you're experiencing impacts beyond what's typical for construction, please contact us directly.
Project Schedule
Schedule Lookahead*
The pipe replacements occur in segments, with crews moving west to east on Courtney Ave. before moving to side streets. Each line of the schedule describes the general area of the pipe segment to be replaced. Please refer to the map or contact the project manager for more details.
| Week of | Location | Planned Work | Potential Impacts |
|---|---|---|---|
| 2/16 - 2/17 | Courtney Ave., just east of the intersection with River Rd. | Pipe bursting and lateral replacements | Courtney Ave. closed between River Rd. & Lee Ave.<br><br> Crews to work with residents to maintain local access |
| 2/18-2/19 | Courtney Ave. just west of SE Lee Ave. | Pipe bursting and lateral replacements | Courtney Ave. closed between River Rd. & Lee Ave.<br><br> Crews to work with residents to maintain local access |
| 2/23 - 2/26 | Courtney Ave. between SE Lee Ave. and SE Rupert Dr. | Pipe bursting and lateral replacements | Work is postponed until Tuesday, 2/24 this week due to weather conditions. <br><br>Courtney Ave. closed between roughly Lee Ave. & Rupert Dr.<br><br> Crews to work with residents to maintain local access |
| 3/2 - 3/6 | Courtney Ave. between approximately Rupert Dr. & Linden Ln. | Pipe bursting and lateral replacements | Courtney Ave. closed between roughly Rupert Dr. & Linden Ln.<br><br> Crews to work with residents to maintain local access |
| 3/9 - 3/12 | Courtney Ave. between approximately Linden Ln. & Courtney Rd. | Pipe bursting and lateral replacements | Courtney Ave. closed between roughly Linden Ln. & Courtney Rd.<br><br> Crews to work with residents to maintain local access |
* Schedule is our best current estimate and is subject to change.